Which describes the 'plan' value chain activity?

Show Answer
Correct Answer: A

The 'plan' value chain activity is focused on ensuring a shared understanding of the current status and vision for all products and services across the organization. This involves aligning strategies and plans to achieve the objectives and creating a unified approach to managing and improving the value chain.

Discussion

5 comments
Sign in to comment
[Removed]Option: A
Apr 28, 2022

A. It ensures a shared understanding of the current status and vision for all products and services across the organization - Plan B. It ensures that services are delivered and supported according to agreed specifications and stakeholders' expectations - Deliver and Support C. It ensures that service components are available when and where they are needed, and meet agreed specifications - Obtain/Build D. It ensures continual improvement of products, services, and practices across all value chain activities - Improve

Rom0817Option: A
Aug 5, 2021

A is ok. The purpose of the plan value chain activity is to ensure a shared understanding of the vision, current status, and improvement direction for all four dimensions and all products and services across the organization.

bigpete975Option: A
Dec 24, 2021

A is correct.

7899388Option: A
Jan 22, 2024

I believe A is correct

DH333Option: A
Nov 15, 2023

A is correct, per definition.