Which describes a CORRECT approach to change authorization?
Which describes a CORRECT approach to change authorization?
Normal changes should be assessed and authorized before they are deployed, as they require careful evaluation to ensure they do not disrupt services or introduce unintended issues. This is in contrast to emergency changes, which might need expedited handling but still require a level of authorization depending on the severity and impact. Additionally, it is not correct to assume that changes in a change schedule are pre-authorized or that normal changes are simply service requests managed by the service desk.
5.2.4 Change enablement Normal changes: These are changes that need to be scheduled, assessed, and authorized following a process. Change models based on the type of change determine the roles for assessment and authorization.
5.2.4 Change enablement All changes should be assessed by people who are able to understand the risks and the expected benefits; the changes must then be authorized before they are deployed.
I think it is B:
B is correct
B is correct.
B - correct.