Question 49

Which statement about change authorities is CORRECT?

    Correct Answer: D

    Change authorities are assigned for each type of change and change model to ensure that the appropriate level of control and authorization is applied to different kinds of changes, whether they are emergency, normal, or standard changes. This allows the organization to follow consistent procedures while adapting to the specific requirements of each change type.

Discussion
TraktarkOption: D

The correct answer is: D. Change authorities are assigned for each type of change and change model. Explanation: Change authorities are responsible for approving and authorizing changes within an organization. The level of authority and the specific roles assigned as change authorities may vary depending on the type of change and the change model being used. Different types of changes, such as emergency changes, normal changes, and standard changes, may require different levels of approval and authorization. The assignment of change authorities ensures that the appropriate individuals or groups are involved in the decision-making process for each type of change, following the established change management procedures.

136898is42Option: D

Standard changes are pre-authorized, someone had to approve the change.

MrTargaryenOption: D

Change authorities = Change Advisory Board (CAB) to review all changes.

bigpete975Option: D

D is correct.

Goodak47Option: D

D is answer

makowskim3Option: C

D or C? Standard is pre auth so rather C?

Zephaniah

C not correct.. the word "only" eliminates it

klezlil

Even if standard change is pre-autorized, it needs to be authorized at least once. So the correct answer is D