ITILFND V4 Exam QuestionsBrowse all questions from this exam

ITILFND V4 Exam - Question 295


Which practice would be MOST involved in assessing the risk to services when a supplier modifies the contract they offer to the organization?

Show Answer
Correct Answer: B,D

The practice most involved in assessing the risk to services when a supplier modifies the contract they offer to the organization is Service Level Management. This practice is responsible for ensuring that the level of service delivered by the supplier meets the organization's needs and requirements as set out in the contract. When a supplier modifies their contract, it can directly impact the service levels they are able to deliver, requiring Service Level Management to assess the potential risks and take appropriate action to maintain or adjust the service levels accordingly.

Discussion

17 comments
Sign in to comment
concepcionzOption: D
Mar 9, 2023

According to ITIL, change enablement is the modification of the company’s IT infrastructure that can lead to a direct or indirect effect on its operations without increasing the associated risk. The modification can be an addition, subtraction, or a switch in the strategy to improve the results. Service Level Management defines, agrees, and monitors service levels with customers and provides a framework for measuring and reporting on service performance. Service-level management examples include defining services and expected delivery times, monitoring service promises and measuring customer satisfaction. Service level management is responsible for ensuring that the level of service delivered by the supplier meets the organization's needs and requirements as set out in the contract. When a supplier modifies their contract, this can have an impact on the service levels that they are able to deliver, and it is therefore important for the service level management practice to assess the potential risks to the services and take appropriate action.

gpfsOption: B
Nov 27, 2022

Answer is B 5.2.4 Key message The purpose of the change enablement practice is to maximize the number of successful service and product changes by ensuring that risks have been properly assessed, authorizing changes to proceed, and managing the change schedule.

Norfana_inaOption: D
Aug 9, 2023

What is the correct answer? Admin should update if the answer was D, so confusing

coolassbreeseOption: D
Jul 6, 2023

D should be correct as it relates to contracts

SamAhamedOption: D
Aug 11, 2023

When a supplier modifies their contract, it can impact the services being provided to the organization, so service level management would be involved in assessing the risk to services and working with the supplier to mitigate any negative impacts.

SoshirazOption: D
Apr 20, 2023

On ne crée pas un changement pour la modification d un contrat d un fournisseur

TraktarkOption: D
Apr 24, 2023

The correct answer is D. Service level management. Service level management is responsible for managing and maintaining the quality of services provided to customers, including managing relationships with suppliers and ensuring that service levels are met. When a supplier modifies their contract, it can impact the services being provided to the organization, so service level management would be involved in assessing the risk to services and working with the supplier to mitigate any negative impacts. Service request management deals with handling customer requests for services, while change enablement is responsible for managing changes to services and ensuring that they are implemented smoothly. Incident management deals with resolving incidents and restoring services as quickly as possible.

[Removed]Option: C
Jul 28, 2023

5.2.5 pg 165 Incident management mayrequire frequent interaction with these suppliers, and routine management of this aspect of supplier contracts is often part of the incident management practice.

AiMoMoOption: D
Aug 3, 2023

D is correct

bdemps98Option: D
Sep 22, 2023

I'm pretty convinced it is option D. It was my first choice, but started second guessing myself after reading some of the B answer comments, but I believe the big indicator is that change enablement doesn't associate with risk. This is not the same for service level management - as a case increases in service level so does the risk associated with it.

thefluffyoneOption: B
Sep 28, 2023

It would be B Base on.the purpose of change enablement: To maximize the number of successful service and product changes by ensuring that risks have been properly assessed, authorizing changes to proceed and managing the change schedule.

Erfan_DenmarkOption: D
Nov 4, 2023

D is correct

Paul_whiteOption: D
Dec 14, 2023

The practice that would be most involved in assessing the risk to services when a supplier modifies the contract they offer to the organization is **D. Service Level Management**. Service Level Management is responsible for ensuring that all current and planned IT services are delivered to agreed achievable targets. This includes assessing the impact of changes in supplier contracts on the service levels. It's worth noting that while all the options listed play important roles in service management, Service Level Management specifically deals with managing and maintaining the service levels which includes dealing with suppliers and contracts.

LeeVeeOption: D
Dec 16, 2023

Absence of Supplier management its should be service level management. Supplier as producer and Consumer would be the organization. Key word is "supplier modifies the contract"

Protocol0Option: B
Feb 11, 2024

Service Level Management (SLM) is indeed involved in managing and negotiating Service Level Agreements (SLAs) and ensuring that all service management processes, operational level agreements, and underpinning contracts are appropriate for the agreed-upon service level targets. SLM is mainly focused on ensuring that the agreed-upon services are delivered as per the contract. However, when it comes to assessing the risk of changes, especially those related to suppliers and contracts, Change Enablement becomes more relevant. Change Enablement is designed to maximize the number of successful IT changes by ensuring that risks have been properly assessed, authorizing changes to proceed, and managing a change schedule.

NetMasterXOption: D
Mar 27, 2024

D correct the answer for god sake.

ManikRoyOption: D
Jun 26, 2024

Service level management is dependent on contract.