ITILFND V4 Exam - Question 141


Which statement about problems is CORRECT?

Show Answer
Correct Answer: D

Problem prioritization involves risk assessment. Problems are analyzed and managed based on the potential impact and probability of risks they pose to the organization. Prioritizing problems this way allows the organization to address the most critical issues that could affect business operations.

Discussion

14 comments
Sign in to comment
arekOption: D
Jan 29, 2021

Correct Answer: D

babatiOption: D
Jan 12, 2021

Problems are: >> prioritized for analysis based on the risk that they pose, and are managed as risks based on their potential impact and probability.

RoxyLoOption: D
Mar 6, 2021

correct answer is D, check the link attached to this question, it indicates is D, B is for Incident.

APAmalaysiaOption: D
Aug 30, 2022

Answer – D . Problem prioritization involves risk assessment. Problems are prioritized for analysis based on the risk that they pose, and are managed as risks based on their potential impact and probability. A. Problems are related to incidents, but should be distinguished as they are managed in different ways. B. Incidents have an impact on users or business processes, and must be resolved so that normal business activity can take place. C. It is important to analyse problems from the perspective of all four dimensions of service management

bgfraymanOption: D
Oct 28, 2021

definitely not B, incidents should be resolved as quickly as possible, problem managaement is slow and could cost time, so D should be correct here.

Pikapika12638Option: D
Aug 5, 2022

D should be prioritized based on risks

SandyIndiaOption: D
Jul 26, 2021

Just like incidents, problems will be prioritized based on the risk they pose in terms of probability and impact to services. Focus should be given to problems that have highest risk to services and service management.

BordewijkOption: D
Sep 28, 2023

Problems are analyzed based on the risk they propose (see ITIL Foundation book 5.2.8)

alter_SOption: D
Oct 10, 2023

5.2.8 / pg.131 Problems are prioritized for analysis based on the risk that they pose, and are managed as risks based on their potential impact and probability. It is not essential to analyse every problem; it is more valuable to make significant progress on the highest-priority problems than to investigate every minor problem that the organization is aware of.

bigpete975Option: D
Dec 24, 2021

D is correct.

xman888888Option: D
Jan 22, 2022

Definitely D

Roro2011Option: D
Mar 12, 2022

D. Problem prioritization involves risk assessment.

louisngOption: D
May 9, 2022

D is correct

jj0097Option: D
Jun 5, 2022

I would say D