ITILFND V4 Exam - Question 179


Which is a low risk change that has been pre-approved so that no additional authorization is needed?

Show Answer
Correct Answer: A

A standard change is a low risk and pre-approved change that is well understood and fully documented, meaning it can be implemented without requiring additional authorization. This is distinct from other types of changes like emergency or normal changes, which require additional scrutiny and approval due to their complexity or urgency.

Discussion

2 comments
Sign in to comment
Rom0817Option: A
Aug 5, 2021

Standard Change A low-risk, pre-authorized change that is well understood and fully documented, and can be implemented without needing additional authorization. Is often initiated as a service request, but may also be an operational change.

bigpete975Option: A
Dec 24, 2021

A is correct.