Question 65

Which practice is responsible for moving new or changed components to live or other environments?

    Correct Answer: B

Discussion
heamguOption: B

The purpose of the deployment management practice is to move new or changed hardware, software, documentation, processes, or any other component to live environments. It may also be involved in deploying components to other environments for testing or staging.

Aman__GOption: B

key words Deployment management live or other enviroment Release management features available for use

Ting3346Option: B

the purpose of the deployment management practice is to moving new or changed hardware, software, documentation, processes or any other service component to live environment.

AtsedeaOption: A

The purpose of the release management practice is to make new and changed services and features available for use.

bigpete975Option: B

B is correct.

peppeOption: B

B is correct

ManikRoyOption: B

The purpose of the deployment management practice is to move new or changed hardware, software, documentation, processes, or any other component to LIVE environments. The purpose of the release management practice is to make new and changed services and features available for use.

BD12Option: B

c'est B qui correct

dufadOption: B

B is correct