ITILFND V4 Exam - Question 65


Which practice is responsible for moving new or changed components to live or other environments?

Show Answer
Correct Answer: B

Discussion

9 comments
Sign in to comment
heamguOption: B
Mar 29, 2021

The purpose of the deployment management practice is to move new or changed hardware, software, documentation, processes, or any other component to live environments. It may also be involved in deploying components to other environments for testing or staging.

Aman__GOption: B
Sep 29, 2023

key words Deployment management live or other enviroment Release management features available for use

AtsedeaOption: A
Mar 25, 2021

The purpose of the release management practice is to make new and changed services and features available for use.

Ting3346Option: B
Dec 17, 2022

the purpose of the deployment management practice is to moving new or changed hardware, software, documentation, processes or any other service component to live environment.

peppeOption: B
Jul 4, 2021

B is correct

bigpete975Option: B
Dec 24, 2021

B is correct.

dufadOption: B
Sep 26, 2022

B is correct

BD12Option: B
Jun 21, 2023

c'est B qui correct

ManikRoyOption: B
Jun 16, 2024

The purpose of the deployment management practice is to move new or changed hardware, software, documentation, processes, or any other component to LIVE environments. The purpose of the release management practice is to make new and changed services and features available for use.