ITILFND V4 Exam QuestionsBrowse all questions from this exam

ITILFND V4 Exam - Question 344


Which of the following statements about change authorization is CORRECT?

Show Answer
Correct Answer: C

The change type and model is the basis for assigning the change authority. Change types, such as standard, normal, and emergency, and their corresponding models help determine who has the authority to approve and manage the change, ensuring the right level of oversight and governance is applied. This approach streamlines the change management process by clearly defining responsibilities based on the nature and criticality of the change.

Discussion

4 comments
Sign in to comment
RogercamposOption: C
Apr 7, 2024

The answer given that makes sense to the topic

dharmaitilOption: A
Apr 9, 2024

A. Every time a standard change is requested a change authority is assigned

e64f19bOption: A
Jun 12, 2024

A is correct

WOW_ThatsCrazyOption: C
Jul 13, 2024

C. The change type and model is the basis for assigning the change authority Change types (standard, normal, emergency) and change models help determine who has the authority to approve and manage the change, ensuring the right level of oversight and governance