ITILFND V4 Exam - Question 279


Which is an activity in the 'problem control' phase of problem management?

Show Answer
Correct Answer: AC

The 'problem control' phase of problem management focuses on identifying, recording, and managing problems to prevent their recurrence. An activity within this phase includes re-assessing a known error to manage its ongoing impact, which helps to ensure it doesn't cause further incidents. This task is aligned with the proactive approach of problem management to prevent future issues.

Discussion

1 comment
Sign in to comment
gpfsOption: C
Nov 25, 2022

Correct is C "Problem control activities include problem analysis, and documenting workarounds and known errors"