Which is a use of the change schedule?
Which is a use of the change schedule?
The change schedule is used to help plan changes, assist in communication, avoid conflicts, and importantly, assign resources to changes. This ensures that all necessary resources are allocated appropriately and that changes are implemented efficiently.
The change schedule is used to help plan changes, assist in communication, avoid conflicts and assign resources.
Answer A Explanation: 5.2.4 Change control - Page 161 The change schedule is used to help plan changes, assist in communication, avoid conflicts, and assign resources.
A is correct
...and preventing conflicts with other (to be) planned changes
A is correct
A IS CORRECT