Which one of the following would you typically expect to find in a test completion report for a test level?
Which one of the following would you typically expect to find in a test completion report for a test level?
A test completion report for a test level typically includes a summary of the testing performed, along with any deviations from the schedule, duration, or effort of test activities. This information provides a comprehensive overview of the testing process and highlights any discrepancies that occurred compared to the original plan. This helps stakeholders understand the test coverage and any issues encountered during the testing phase.
I think it is B
I think its B from syllabus https://astqb.org/assets/documents/CTFL-2018-Syllabus.pdf page 71 "When exit criteria are reached, the test manager issues the test summary report. This report provides a summary of the testing performed, based on the latest test progress report and any other relevant information. Typical test summary reports may include: • Summary of testing performed • Information on what occurred during a test period • Deviations from plan, including deviations in schedule, duration, or effort of test activities"
B. A summary of the testing performed and any deviations from the schedule, duration, or effort of test activities. A test completion report for a test level typically includes a summary of the testing that was performed during that level, along with any deviations from the planned schedule, duration, or effort of test activities. This information provides an overview of the test activities that took place and highlights any discrepancies from the original plan.
Responsable du site : Reponse B Merci de corriger SVP