Which of the following is an example of a typical project risk?
Which of the following is an example of a typical project risk?
A typical project risk involves factors that can negatively impact the ability to meet project objectives. In this case, the risk that the developers may not have the right skills to code the application is a common example of such a project risk. This risk can directly affect the timeline and successful completion of a project, making it a fundamental concern in project management.
If you can write a test for it, it’s a product risk. Correct answer is C.
I think its C, from syllabus: page 73 "Project risk involves situations that, should they occur, may have a negative effect on a project's ability to achieve its objectives. Examples of project risks include: ... Organizational issues: o Skills, training, and staff may not be sufficient "
I think that the correct answer should be: C