Exam CTFL All QuestionsBrowse all questions from this exam
Question 4

Which of the following risks represents the highest level of risk to the project?

    Correct Answer: B

    To determine the highest level of risk to the project, we calculate the expected cost of impact for each option, which is the product of the likelihood of failure and the potential cost of impact. For option A: 1% of $1,000,000 equals $10,000. For option B: 10% of $500,000 equals $50,000. For option C: 20% of $150,000 equals $30,000. For option D: 5% of $500,000 equals $25,000. Option B has the highest expected cost of impact, therefore it represents the highest level of risk to the project.

Discussion
laraerfOption: B

B is correct

MthethoOption: B

B. Likelihood of failure = 10%, potential cost of impact = $500,000.

Suraj_RajOption: D

Correct Ans - D

Jyoti27Option: B

Likelihood to fail and impact is higher

Aditya_BodakeOption: D

The answer should be D because the failure is 5 % and the impact for it is 5,00,000. which is high than the option B.