CTFL Exam QuestionsBrowse all questions from this exam

CTFL Exam - Question 4


Which of the following risks represents the highest level of risk to the project?

Show Answer
Correct Answer: B

To determine the highest level of risk to the project, we calculate the expected cost of impact for each option, which is the product of the likelihood of failure and the potential cost of impact. For option A: 1% of $1,000,000 equals $10,000. For option B: 10% of $500,000 equals $50,000. For option C: 20% of $150,000 equals $30,000. For option D: 5% of $500,000 equals $25,000. Option B has the highest expected cost of impact, therefore it represents the highest level of risk to the project.

Discussion

5 comments
Sign in to comment
Aditya_BodakeOption: D
May 11, 2022

The answer should be D because the failure is 5 % and the impact for it is 5,00,000. which is high than the option B.

Jyoti27Option: B
Jul 13, 2022

Likelihood to fail and impact is higher

Suraj_RajOption: D
Jan 20, 2023

Correct Ans - D

MthethoOption: B
Feb 19, 2023

B. Likelihood of failure = 10%, potential cost of impact = $500,000.

laraerfOption: B
Jun 8, 2023

B is correct