Which of the following metrics could be used to monitor progress along with test preparation and execution?
Which of the following metrics could be used to monitor progress along with test preparation and execution?
Monitoring the total number of tests planned helps track progress in both test preparation and execution. This metric allows the team to gauge how much of the overall testing effort has been outlined and how much remains. It provides a clear picture of the planning stages and aligns well with the tracking of test execution as the tests are completed against the planned total.
C is correct, because A is not about execution
A is correct #chatgpt