Which of the following is the GREATEST risk of project dashboards being set without sufficiently defined criteria?
Which of the following is the GREATEST risk of project dashboards being set without sufficiently defined criteria?
Undefined criteria in dashboards risk embedding biases (e.g., prioritizing visually appealing metrics over meaningful ones) or misrepresenting data through flawed models.Decision-makers often conflate design quality with data accuracy, leading to "poor decisions with confidence." This directly impacts prioritization and strategic outcomes, making B the most critical risk.