CISA Exam QuestionsBrowse all questions from this exam

CISA Exam - Question 692


The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed. Which of the following should the audit manager do FIRST?

Show Answer
Correct Answer: BD

The first step for the audit manager should be to determine where delays have occurred. This will help identify the root causes of the delay and guide the manager in making informed decisions about the next steps. By understanding the specific reasons for the delay, the manager can decide whether to assign additional resources, extend the deadline, or escalate the issue if necessary. Addressing the root cause is essential before taking any further action.

Discussion

6 comments
Sign in to comment
TEC1Option: D
Feb 8, 2023

D. Determine where delays have occurred. Before taking any action to address the delay in the audit project, it is important for the audit manager to determine the cause of the delay. This will help the audit manager to identify the root cause and make informed decisions on how to address the situation. Understanding where the delays have occurred will help the audit manager to better allocate resources and make changes to the project plan to ensure that the audit is completed on time. Only after the cause of the delay has been determined can the audit manager consider options such as extending the deadline, assigning additional resources, or escalating to the audit committee.

JONESKAOption: D
Jul 20, 2023

While extending the audit deadline (option A) or assigning additional resources (option C) might be viable options, it is essential to first determine the reasons for the delays to make informed decisions about the best course of action. Escalating to the audit committee (option B) should only be considered if there are significant issues or impediments that cannot be resolved at the managerial level. Therefore, the FIRST step for the audit manager is to determine where delays have occurred which is Option D, this will then enabling them to develop a well-informed and targeted plan to address the audit completion challenges.

starzuuOption: D
Jul 29, 2023

i think its D.

Deeplaxmi
Sep 21, 2022

can anyone explain why this is the right answer?

vipulsinghal2903Option: B
Sep 25, 2022

A - you cannot extend audit deadline yourself C - Same reason as above. D - this will be done post completion.

RS66Option: D
Jul 12, 2024

D. The manager needs to determine the reason of the delay before taking action.