Before the release of a new application into an organization's production environment, which of the following should be in place to ensure that proper testing has occurred and rollback plans are in place?

Show Answer
Correct Answer: D

Before the release of a new application into an organization's production environment, a Change Approval Board (CAB) should be in place to ensure that proper testing has occurred and rollback plans are in place. The CAB reviews and approves changes to the IT environment, including new applications or updates, to ensure they meet quality standards and do not negatively impact the production environment.

Discussion

4 comments
Sign in to comment
saado9Option: B
May 6, 2023

B. Standardized change requests

FAGFUROption: D
Nov 13, 2023

Before the release of a new application into an organization's production environment, having a Change Approval Board in place is important to ensure that proper testing has occurred and rollback plans are in place. The CAB is responsible for reviewing and approving changes to the IT environment, including new applications or updates, to ensure that they meet quality standards and do not adversely impact the production environment.

RachyOption: B
Jan 22, 2024

B. Standardized change request

SwallowsOption: D