CISA Exam - Question 410


Which of the following is the BEST point in time to conduct a post-implementation review (PIR)?

Show Answer
Correct Answer: CD

The best time to conduct a post-implementation review (PIR) is after a full processing cycle. This timing allows the system to be thoroughly tested in a real-world environment, ensuring that its performance, stability, and impact on operations can be accurately assessed. Any issues that might not be immediately apparent post-deployment will likely surface during regular operational cycles, providing a comprehensive evaluation of the implementation's success and its alignment with business requirements.

Discussion

10 comments
Sign in to comment
DeeplaxmiOption: C
Oct 2, 2022

i think C- after a full processing cycle would be a better answer.

zebreeOption: C
Feb 4, 2023

The BEST point in time to conduct a post-implementation review (PIR) is "After a full processing cycle." This allows the system to be tested in a real-world scenario, and any issues can be addressed in a timely manner.

swmasindeOption: D
Mar 13, 2023

PIR is done 2 to 6 weeks after implementation

David_HuOption: C
Jan 7, 2023

should be C

Mark_1Option: D
May 24, 2023

https://www.metapm.com.au/insights/post-implementation-review-best-practices#:~:text=The%20perfect%20time%20to%20conduct,fresh%20in%20the%20users'%20minds. The perfect time to conduct a PIR is between 2 to 6 weeks after project completion. This gives the project enough time to be in use, yet, still fresh in the users' minds.

JustCisaOption: C
Oct 30, 2023

C. After a full processing cycle. Conducting a PIR after a full processing cycle allows for a comprehensive assessment of the new system's performance, stability, and its impact on regular operations. This timing ensures that any issues or anomalies that might not have been apparent during initial deployment or immediately afterward can be identified and addressed. It provides a more accurate representation of the system's functionality and performance under typical working conditions.

KAP2HURUFOption: C
Mar 3, 2024

Conducting a PIR after a full processing cycle allows for a comprehensive assessment of the system's performance and effectiveness in handling real-world data and transactions. This approach ensures that the review captures a complete picture of the system's functionality, identifies any issues or challenges encountered during regular operations, and evaluates the system's ability to meet business requirements over time.

hohoOption: D
Jun 24, 2023

Six week? How to measure if super big project, it difficult to said

a84nOption: D
Apr 28, 2024

Answer: D Ref CISA RM 27th edition - 3.8 Post-implementation review Page: 171 (In contrast to project closure, a post-implementation review typically is carried out in several weeks or months after project completion)

SwallowsOption: C
Jun 8, 2024

While conducting a PIR six weeks after deployment (Option D) may provide some initial insights into the immediate performance and stability of the implemented changes, it may not capture the full range of system usage and effects over time. Waiting for a full processing cycle allows for a more comprehensive and meaningful review of the implementation's success and its alignment with organizational objectives.