Explanation:
While all the options provided have their merits, focusing on the high-priority risks through qualitative risk analysis is the most strategic approach for several reasons:
Resource Allocation:
By focusing on high-priority risks, you ensure that your limited resources (time, money, expertise) are allocated to the risks that could have the most significant impact on the project.
Impact on Project Performance:
Addressing high-priority risks first can significantly improve the project's performance by mitigating or avoiding the most severe potential issues that could derail the project.
Stakeholder Engagement:
High-priority risks are likely to be of greater concern to key stakeholders. Addressing these risks can help in maintaining stakeholder confidence and support throughout the project.
Why the Other Options are Less Optimal:
A. Involve subject matter experts in the risk analysis activities: