CRISC Exam QuestionsBrowse all questions from this exam

CRISC Exam - Question 45


You are a project manager for your organization and you're working with four of your key stakeholders. One of the stakeholders is confused as to why you're not discussing the current problem in the project during the risk identification meeting. Which one of the following statements best addresses when a project risk actually happens?

Show Answer
Correct Answer: C

According to project management principles, a project risk is something that may happen in the future. It is an uncertain event or condition that, if it occurs, will have a positive or negative impact on one or more project objectives. If the event has already occurred, it is no longer a risk but an issue, which needs to be addressed through issue management processes. Therefore, discussing current problems in a risk identification meeting is not appropriate as they are not risks but existing issues.

Discussion

4 comments
Sign in to comment
bnyk123
Oct 17, 2020

This question is confusing and poorly worded.

Shaws1
Mar 7, 2021

question is not correct and poorly articulated

FluffyMalware
May 5, 2021

very poorly worded question

JolomsOption: C
May 31, 2024

The best statement to address this distinction is: "Project risks are potential future events that may impact the project if they occur, whereas the current problem you mentioned is an issue that we are already facing and needs to be managed through our issue resolution process. In risk identification meetings, we focus on identifying and planning for potential future risks to mitigate their impact on the project."