CISM Exam QuestionsBrowse all questions from this exam

CISM Exam - Question 1109


Who should decide whether a specific control should be changed once risk is approved for mitigation?

Show Answer
Correct Answer: C

The control owner is responsible for the implementation, monitoring, and adjustment of controls to address identified risks. Once a risk is identified and approved for mitigation, it is within the control owner’s authority to decide whether a specific control should be changed to ensure it remains effective and aligned with the organization's risk management objectives.

Discussion

1 comment
Sign in to comment
BooictOption: C
Jul 18, 2024

C-he control owner oversees the implementation, monitoring, and adjustment of controls to address identified risks. They ensure that controls remain effective and aligned with risk management objectives