Exam CBAP All QuestionsBrowse all questions from this exam
Question 191

Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?

    Correct Answer: C

    The Critical Path Method (CPM) is most appropriate for presenting a project plan to upper management. CPM is a step-by-step project management technique that identifies critical and non-critical tasks with the goal of preventing time-frame problems and process bottlenecks. Unlike pie charts, Pareto charts, or scatter charts, CPM provides a detailed temporal flow of tasks, showing the longest path of planned activities to the end of the project, which is essential for high-level project oversight and decision-making by upper management.

Discussion
Alwaysmoses

i think they mixed up PMBOK questions here. this question is not a Cbap question

UppersquareCapital

Some of these questions are out of scope, they are not CBAP questions but for Project Management exams, I guess

OlivierPaudexOption: C

critical path method = simple diagram for real-time visibility. Good to explain project to newbies. Not in BABOK v3

MFZZ

Which section of BABOK v3 (and page)

MFZZ

Where is this in BABOKv3?

ElyonSenjo

it's out of BABOK v3