CBAP Exam - Question 208


Which of the following defines the deliverable the customer is expecting?

Show Answer
Correct Answer: C

The product scope statement defines the deliverable that the customer is expecting. It outlines the entire project, including the deliverables and their features. This document ensures that both the project team and the customer have a clear understanding of what the final product or service will include.

Discussion

2 comments
Sign in to comment
NickManeOption: C
Aug 27, 2021

C stands for Correct - Typically written by the project manager, a scope statement outlines the entire project, including any deliverables and their features,

b9adaf1Option: A
Feb 12, 2024

Nothing about product scope statement in V3