Question 189

As a program manager, you decided to overlap two phases of your program.

Which of the following terms best describe your act?

    Correct Answer: C

    Overlapping two phases of a program is best described by the term 'fast tracking'. Fast tracking is a schedule compression technique where tasks that are normally done in sequence are performed concurrently to shorten the project timeline.

Discussion
Alwaysmoses

why are we seeing Pmp questions on Cbap simulations here? is it an error?

ElyonSenjo

BABOK v2

OctavianGOption: C

The PMBOK Guide, 6th edition, defines fast-tracking as a schedule compression technique in which activities or phases normally performed in a sequence are done in parallel for at least a portion of their duration.