Question 122

Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?

    Correct Answer: B

    Work performance information is the input that acquires information from performance measurements and evaluates it to provide variance analysis and forecasting. This information helps assess the current status of risks, monitor their progress, and identify any emerging risks or changes in risk conditions.

Discussion
Inzaghi78Option: B

B. Work performance information In the Monitor and Control Risks process, work performance information is the input that acquires information from performance measurements and evaluates it to provide variance analysis and forecasting. This information helps assess the current status of risks, monitor their progress, and identify any emerging risks or changes in risk conditions. Therefore, option B is the correct choice.