Question 86

When is stakeholder analysis performed?

    Correct Answer: A

    Stakeholder analysis is performed as soon as the project charter is created. The project charter formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. At this stage, identifying and analyzing stakeholders is essential to understand their needs, expectations, potential impact on the project, and to ensure their engagement throughout the project lifecycle.

Discussion
Chu2Option: C

Stakeholder analysis is usually done once a business need is identified

RfcuencaOption: C

Option C Babok v2 Page 24