CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 86


When is stakeholder analysis performed?

Show Answer
Correct Answer: A

Stakeholder analysis is performed as soon as the project charter is created. The project charter formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. At this stage, identifying and analyzing stakeholders is essential to understand their needs, expectations, potential impact on the project, and to ensure their engagement throughout the project lifecycle.

Discussion

2 comments
Sign in to comment
RfcuencaOption: C
Jan 16, 2024

Option C Babok v2 Page 24

Chu2Option: C
Jul 21, 2024

Stakeholder analysis is usually done once a business need is identified