Question 18

In addition to schedule, which other factor must be considered when evaluating changes to requirements?

    Correct Answer: A

    When evaluating changes to requirements, in addition to the schedule, it is essential to consider the number of customers and end-users affected. This helps in understanding the impact of the change on the stakeholders and ensures that the business impact is taken into account.

Discussion
Adnan8t2Option: A

ANSWER: A Page 93 – BABOK V3 When considering changes or additions to existing requirements, business analysts assess the impact of the proposed change by considering: Impact: the number of customers or business processes affected if the change is accepted.

sopalOption: A

i second Hazemnz, page 93 : Impact: the number of customers or business processes affected if the change is accepted. but i would also point to page 91 : • affects value delivered to the business or stakeholder groups,

HazemnzOption: A

BABOK page 93