In addition to schedule, which other factor must be considered when evaluating changes to requirements?
In addition to schedule, which other factor must be considered when evaluating changes to requirements?
When evaluating changes to requirements, in addition to the schedule, it is essential to consider the number of customers and end-users affected. This helps in understanding the impact of the change on the stakeholders and ensures that the business impact is taken into account.
ANSWER: A Page 93 – BABOK V3 When considering changes or additions to existing requirements, business analysts assess the impact of the proposed change by considering: Impact: the number of customers or business processes affected if the change is accepted.
i second Hazemnz, page 93 : Impact: the number of customers or business processes affected if the change is accepted. but i would also point to page 91 : • affects value delivered to the business or stakeholder groups,
BABOK page 93