As a business analyst, you may be called upon to define the scope of work and to develop the estimates for the endeavor. Which one of the following is an important tool for this activity?
As a business analyst, you may be called upon to define the scope of work and to develop the estimates for the endeavor. Which one of the following is an important tool for this activity?
As a business analyst, an important tool for defining the scope of work and developing estimates is the Work Breakdown Structure (WBS). The WBS helps decompose the project scope into smaller, more manageable pieces, which can then be broken down further into iterations, releases, phases, work packages, or tasks. This hierarchical decomposition allows for a clear understanding of the work involved and aids in more accurate estimation and scope definition.
Project management plan
Correct Answer is B