Question 108

A business analyst (BA) has identified the impacts and resolution for a proposed change. Based on the Responsible, Accountable, Consulted, Informed (RACI) matrix, who must approve the change before it is implemented?

    Correct Answer: B

    In a RACI matrix, the person assigned as 'Accountable' is typically the one who must approve changes before they are implemented. This is often the Business Sponsor, who holds overall accountability for the success of the project and ensures that changes align with business goals and standards.

Discussion
CheburaatorsOption: D

System architect

Thunderbird35Option: B

answer is B