Exam CCBA All QuestionsBrowse all questions from this exam
Question 14

Kendra is the business analyst for her organization. She's working with the project manager and the project sponsor to discuss the current requirements. Kendra believes it's important for the project manager to first implement the requirements with the highest amount of risks. Is this a good idea?

    Correct Answer:

    Implementing the high-risk requirements first can be beneficial because it allows the project team to address potential issues early in the schedule. By tackling these risks upfront, the project can effectively assess whether the project goals are achievable within the constraints of time, budget, and resources. If there are insurmountable problems, discovering them early means that less investment has been made, thereby reducing potential loss. This strategy is generally considered good practice in risk management to ensure that significant challenges are identified and addressed as soon as possible.

Discussion
Stella9711Option: B

Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.

JennKOHOption: B

B. Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.

Elli_Low1990Option: B

Correct Answer is B

Stella9711Option: D

Yes, this allows the project manager to get the risky work done as soon as possible in the schedule.

rahulpatil_analystOption: B

Correct Answer is B