CCBA Exam QuestionsBrowse all questions from this exam

CCBA Exam - Question 14


Kendra is the business analyst for her organization. She's working with the project manager and the project sponsor to discuss the current requirements. Kendra believes it's important for the project manager to first implement the requirements with the highest amount of risks. Is this a good idea?

Show Answer
Correct Answer:

Implementing the high-risk requirements first can be beneficial because it allows the project team to address potential issues early in the schedule. By tackling these risks upfront, the project can effectively assess whether the project goals are achievable within the constraints of time, budget, and resources. If there are insurmountable problems, discovering them early means that less investment has been made, thereby reducing potential loss. This strategy is generally considered good practice in risk management to ensure that significant challenges are identified and addressed as soon as possible.

Discussion

5 comments
Sign in to comment
Stella9711Option: B
Apr 23, 2023

Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.

rahulpatil_analystOption: B
Jan 27, 2023

Correct Answer is B

Stella9711Option: D
Apr 23, 2023

Yes, this allows the project manager to get the risky work done as soon as possible in the schedule.

Elli_Low1990Option: B
Aug 13, 2023

Correct Answer is B

JennKOHOption: B
Sep 5, 2023

B. Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn't invested much time or money on the project.