Exam CBAP All QuestionsBrowse all questions from this exam
Question 143

Your organization is using a plan-driven approach to business analysis.

What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for?

    Correct Answer: C

    In a plan-driven approach to business analysis, the communications management plan provides the framework for managing all communications documents. It outlines how communication will be handled, including what to do with those documents once the project is completed. Therefore, the communications management plan dictates the procedures and policies for handling all business analysis communications.

Discussion
binu801Option: D

Answer explanation- nothing is destroyed, there is no role as solution project manager in BABOK, C is incorrect as its asking what to do with Comms plan , not whats its purpose. D is correct as all these records are stored and archived for future references

Inzaghi78Option: C

The correct answer is C. The communications management plan will dictate what will happen to the business analysis communications

Farooq_95Option: C

Correct answer is communications management plan will dictate what will happen to the business analysis communications. As per BABOK v3 3.2.4.3, Communication considerations can be documented in the form of a stakeholder communication plan. Business analysts build and review communication plans with stakeholders to ensure their communication requirements and expectations are met.