Question 133

Which of the following is a process of adding labor to a project to reduce the project duration?

    Correct Answer: D

    Crashing is a project management technique used to shorten the schedule duration for the least incremental cost by adding resources. It involves allocating additional labor or resources to critical path activities to reduce their duration, thereby reducing the overall project duration.

Discussion
em1235678Option: D

Couldn't find this in BABOK V3, i'm assuming crashing is a V2 term. Can anyone confirm?

ElyonSenjo

yep I can confirm it

OlivierPaudex

the only term that is still valid in V3 is the rolling-wave, which is an estimation technique

ElyonSenjoOption: D

BABOK v2

SisichelsOption: D

it is in project management, schedule compression techniques

OlivierPaudexOption: D

Yes, correct Project crashing in project management is a method used to speed up a project's timeline by adding additional resources without changing the scope of the project.