Which of the following is a process of adding labor to a project to reduce the project duration?
Which of the following is a process of adding labor to a project to reduce the project duration?
Crashing is a project management technique used to shorten the schedule duration for the least incremental cost by adding resources. It involves allocating additional labor or resources to critical path activities to reduce their duration, thereby reducing the overall project duration.
Couldn't find this in BABOK V3, i'm assuming crashing is a V2 term. Can anyone confirm?
yep I can confirm it
the only term that is still valid in V3 is the rolling-wave, which is an estimation technique
BABOK v2
it is in project management, schedule compression techniques
Yes, correct Project crashing in project management is a method used to speed up a project's timeline by adding additional resources without changing the scope of the project.