Exam CBAP All QuestionsBrowse all questions from this exam
Question 39

You are the business analyst for your organization and you are preparing the business case for a proposed solution. You need to include the management horizon in your business case.

What is the management horizon?

    Correct Answer: D

    The management horizon refers to the point in time for the solution to break even on cost and begin earning a profit. It is when the organization expects to recover its investment and start seeing financial benefits from the solution.

Discussion
Rsolan

Don;t think this is in V3

cert_diwanaOption: B

n a business case, the management horizon typically refers to the project's completion date, while the "break-even point" or "payback period" addresses the financial aspect of when the project starts generating a profit.

HimonOption: D

Correct Ans is D

Bunlizlaw

The Management Horizon is the overall timespan an individual can independently plan and act to achieve a goal under conditions of uncertainty. That is in a state of autonomy.

Bunlizlaw

So I will go with C.Keyword here is "duration".

ElyonSenjo

BABOK v2

MFZZ

I thought Management Horizon was related to the Agile Extension of the BABOK v3? Haven't seen in mentioned in BABOK v3