CBAP Exam - Question 230


Which of the following is a graphical representation of roles and responsibilities of different project team members?

Show Answer
Correct Answer: A

A RACI chart is a graphical representation that outlines the roles and responsibilities of different project team members. It specifically details who is Responsible, Accountable, Consulted, and Informed for each task within a project.