Question 5

Tracy is a business analyst for her organization and she's gathered and identified the needed requirements for the solution scope. What must Tracy do before she can begin managing the requirements? Choose the best answer.

    Correct Answer:

    Before Tracy can begin managing the requirements, she must communicate the requirements to the stakeholders for their consent and approval. This ensures that all stakeholders are on the same page and agree with the identified requirements before moving forward with further actions like decomposition or cost-benefit analysis.

Discussion
FadjOption: D

The answer should be D

JennKOHOption: D

D. Tracy must communicate the requirements to the stakeholders for their consent and approval.

CheburaatorsOption: D

communicate the requirements to the stakeholders

kal5Option: D

The answer should be D

Stella9711Option: D

Tracy must communicate the requirements to the stakeholders for their consent and approval