Question 38

Management has asked you, a business analyst for your organization, to create the solution scope for an identified problem. In order to complete this task, you'll need three elements.

All of the following are elements you'll need in order to write the solution scope except for which one?

    Correct Answer: A

    A work breakdown structure (WBS) is often part of detailed project planning and is used to decompose the project into manageable sections. However, it is not typically a direct component of the solution scope. The solution scope generally includes defining what the solution will achieve, its boundaries and constraints, major features or components, and the implementation approach.

Discussion
rmr29

Admin, please remove BABoK v2 questions from the question bank. Thank you.

cert_diwanaOption: A

While a work breakdown structure (WBS) is an important part of project planning and management, it is not typically considered a direct component of the solution scope. The solution scope primarily includes the definition of what the solution is expected to achieve, the boundaries and constraints, the major features or components, and the high-level implementation approach.

Farooq_95Option: A

Specifically refers to BABOK v2 Task 4.5, not BABOK v3