Question 231

Which of the following techniques is used to divide a project into controllable parts?

    Correct Answer: C

    The technique used to divide a project into controllable parts is Work Breakdown Structure (WBS). WBS is a method that breaks down a project into smaller, manageable sections or tasks to enhance manageability, organization, and clarity in project management.

Discussion
NorieRoseOption: C

Work Breakdown Structure (WBS)