Question 19

You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

    Correct Answer:

Discussion
Stella9711Option: B

Stakeholder management strategy

OZMagsOption: B

Answer is B