CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 172


Which of the following reports is generated whenever the project is slipping off the project schedule and includes an explanation of the problem?

Show Answer
Correct Answer: BC

A delay report is generated whenever the project is slipping off the project schedule and includes an explanation of the problem. A status report provides a general update on the project's progress. A schedule variance report focuses on differences between planned and actual schedules but may not necessarily explain the problem. A cost variance report deals with discrepancies between budgeted and actual costs. Therefore, a delay report is the most appropriate document to address the issue described in the question.

Discussion

2 comments
Sign in to comment
ElyonSenjoOption: B
May 8, 2022

Thre is not an accurate reference in BABOK v3 to this report, but you can handle the correct answer thinking about the meaning of variance and the context of the question.

NorieRoseOption: A
Feb 9, 2024

Status Report