CBAP Exam - Question 219


Which of the following is the comparison of planned project results with actual project results?

Show Answer
Correct Answer: A

Variance analysis is the comparison of planned project results with actual project results. This technique involves identifying and analyzing the differences between these planned and actual outcomes to determine any variances and understand their causes. This helps in managing and controlling project performance.

Discussion

2 comments
Sign in to comment
OctavianGOption: A
Oct 3, 2021

Variance analysis can be summarized as an analysis of the difference between planned and actual numbers.

RabbitsfootOption: A
Mar 9, 2024

BABOK V3 pg 172 .5 Performance Variances: The difference between expected and actual performance represents a variance that is considered when analyzing solution performance.