Exam CBAP All QuestionsBrowse all questions from this exam
Question 25

You are the business analyst for your organization and are working with Jennifer to conduct stakeholder analysis. You would like to create a RACI chart to help with the roles of the people involved in the stakeholder analysis process. Jennifer is not familiar with this chart and asks what does RACI mean.

Which one of the following best describes the RACI chart in the conduct stakeholder analysis process?

    Correct Answer: A

    A RACI chart is a matrix that uses the Responsible, Accountable, Consult, and Inform tasks as part of the stakeholder analysis process. It helps define and document the roles and responsibilities of individuals involved in the project, ensuring clarity and alignment among stakeholders.

Discussion
lanogq2Option: A

Answer: A BABOK v3 10.43.3.3 pg 346