Question 402

In a risk assessment exercise of a software implementation program, the business analyst (BA) has successfully computed the probability of occurrence (POC) and the cost of impact for each of the identified risks as follows:

Which of the following will have the highest negative impact to value?

    Correct Answer: D

    To determine the highest negative impact, we calculate the expected impact for each risk by multiplying the probability of occurrence (POC) by the cost of impact. For 'Natural disasters': 0.2 * 15000 = 3000 USD, for 'Power surges': 0.5 * 20000 = 10000 USD, for 'Human errors': 0.9 * 3000 = 2700 USD, for 'System security': 0.4 * 16000 = 6400 USD. The highest expected impact is from 'Power surges' at 10000 USD.

Discussion
siliconvalleykamOption: D

Make a new list with the Probability of occurrence * Cost of impact and select the highest, that will be 10,000 for Power Surge.

786NB786Option: D

D- power surge Impact times probably and you get 10000 for power surge