Question 197

Which of the following processes includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and the stakeholders' tolerances?

    Correct Answer: A

    The correct answer is the risk management plan. The risk management plan includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and stakeholders' tolerances. It is a comprehensive document that guides how risk management activities are conducted throughout the lifecycle of the project.

Discussion
OctavianGOption: A

A risk management plan also called a “risk mitigation plan” is a well-defined document that tells how to deal with specific risks and what management actions must be taken against those risks in order to mitigate or remove threats to the project tasks and outcomes. The risk management plan gives teams a sense of measures they need to take in order to identify, analyze, and respond to all the risks running around within the project wheel.

HobicOption: A

A risk management plan is not a process