CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 356


The performance of a newly implemented document management system is falling significantly short of the measures defined as part of the project. However, the business is recognizing some level of value from the system. The business analyst (BA) considers the only option available to the company to increase performance and determines that the cost of implementing the option is ten times higher than the expected benefits. What should the BA recommend?

Show Answer
Correct Answer: CD

The business is recognizing some level of value from the implemented document management system even though it is falling short of the expected performance measures. Given that the cost of implementing the only available option to increase performance is ten times higher than the expected benefits, the most prudent and cost-effective decision would be to continue with the implemented solution, as it already provides some value. Retiring the solution or conducting further elicitation would not be justified given the high costs and the existing value derived from the system.

Discussion

7 comments
Sign in to comment
SairaOption: D
Feb 14, 2021

Answer is D : Do nothing

Qualms
Mar 20, 2021

"the business is recognizing some level of value from the system" and the cost of a new solution outweighs the benefit. Hence, Do Nothing is correct. Option D

xiaoyangwuOption: D
Sep 19, 2023

Do Nothing: is usually recommended when the value of a change is low relative to the effort required to make the change, or when the risks of change significantly outweigh the risks of remaining in the current state.

Ray81Option: B
Mar 18, 2021

Answer is B. Current situation shows that the solution is falling short of the expected benefit, and then cost benefit analysis shows that the potential cost outweighs the benefit (10 times!)

DoomsdayNair
Jan 18, 2021

Plan stakeholder engagement - Already Done; Retire the implemented solution - Newly Implemented system also this decision is pending; Continue with the implemented solution - This decision is pending

DoomsdayNairOption: C
Jan 19, 2021

C. Conduct elicitation

[Removed]
Sep 17, 2023

No such option in the element 'Recommendations' p.183

ccie_cbapOption: D
Jun 12, 2021

Answer D- 'Continue with implemented solution' as it is providing some value.

SunlordOption: D
Jan 3, 2022

"The business analyst (BA) considers the only option available to the company to increase performance and determines that the cost of implementing the option is ten times higher than the expected benefits" This is the only option available, the next to it is "do nothing" - D