CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 108


You have completed the requirements documentation and the stakeholders have signed off on the requirements. Now the requirements are advancing into a project as your organization has chartered a project based on the identified requirements.

What stakeholder is now responsible for assessing the solution scope to determine the project scope?

Show Answer
Correct Answer: BC

The business analyst is responsible for assessing the solution scope to determine the project scope. The business analyst defines the characteristics, features, and functions of the solution to be implemented. While the project manager is responsible for managing the project scope, which includes all the work that needs to be performed by the project team, it is the business analyst who specifically assesses and defines the details of the solution scope to ensure it aligns with the project requirements and objectives.

Discussion

8 comments
Sign in to comment
binu801Option: B
Jul 12, 2021

is the project manager is the answer, generally scope is defined by the sponsor

NickMane
Aug 24, 2021

Project manager determents Project scope, Sponsors authorize the work to be performed, and control the budget and scope for the initiative

v72Option: B
Feb 5, 2022

Project Manager: responsible for managing change and planning the detailed activities to complete a change. In a project, the project manager is responsible for the project scope, which covers all the work to be performed by the project team. BABOk v3. p. 131

ShoreyOption: A
Oct 30, 2022

I think it's A. This is what Babok V3 (2.4.7, 2.4.9) says Project managers are responsible for managing the work required to deliver a a solution that meets a business need, and for ensuring that the project's objectives are met while balancing the project factors including scope, budget, schedule, resources, quality, and risk. Sponsors authorize the work to be performed, and control the budget and scope for the initiative.

LaDebzOption: B
Oct 10, 2022

PROJECT MANAGER

Dillon91Option: A
Jan 26, 2023

A: pg 98

RfcuencaOption: B
Jan 18, 2024

Option B Babok v2 page 67

jeffreyokonkwo_Option: C
Feb 16, 2024

I'll go for C Project Scope: Project Scope includes all the work that needs to be done to create a product, or deliver a service or result. Project Scope is all about the project; it defines the work required to create and deploy the product. The project manager prepares the project scope statement. Solution Scope: The Product or Solution Scope is the characteristics, features, or function of the product or service that is to be built. Solution scope is all about the solution to be implemented: how will it look like, how will it function, and other characteristics, etc. A business analyst prepares the product or solution scope.

Farooq_95Option: B
May 3, 2024

BABOK v3 6.4.7 states Project Manager is responsible for managing change and planning the detailed activities to complete a change. In a project, the project manager is responsible for the project scope, which covers all the work to be performed by the project team.