Exam CBAP All QuestionsBrowse all questions from this exam
Question 206

Which of the following chart shows the correlation between project team members and the work they've been assigned to complete?

    Correct Answer: D

    The chart that shows the correlation between project team members and the work they've been assigned to complete is the RACI chart. A RACI chart is a type of Responsibility Assignment Matrix (RAM), but more specifically, it identifies who is Responsible, Accountable, Consulted, and Informed for each task or deliverable. This level of detail directly maps team members to their responsibilities, making it the correct answer.

Discussion
NickMane

Also RACI chart

DoktorKrossOption: D

RACI and RAM charts are technically the same. But for the sake of BABOK, it should be RACI because the Responsibility Assignment Matrix is under PMBOK.

NickManeOption: D

I'd go with RACI

EkyOption: B

RACI is a type of RAM chart

Farooq_95Option: D

The question pertains to PMBOK. Its V7 defines Responsibility Assignment Matrix (RAM) as a grid that shows the project resources assigned to each work package. In the context of BABOK v3, RACI chart is correct answer because it involves assigning the RACI designation in order to specify the level of responsibility expected from each stakeholder and/or group. BABOK v3 does not define RAM.

Dillon91Option: D

RACI chart

Hong_iOption: B

Couldn't find RAM in V3