CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 206


Which of the following chart shows the correlation between project team members and the work they've been assigned to complete?

Show Answer
Correct Answer: BD

The chart that shows the correlation between project team members and the work they've been assigned to complete is the RACI chart. A RACI chart is a type of Responsibility Assignment Matrix (RAM), but more specifically, it identifies who is Responsible, Accountable, Consulted, and Informed for each task or deliverable. This level of detail directly maps team members to their responsibilities, making it the correct answer.

Discussion

7 comments
Sign in to comment
NickMane
Jul 11, 2021

Also RACI chart

EkyOption: B
Jul 13, 2021

RACI is a type of RAM chart

NickManeOption: D
Aug 27, 2021

I'd go with RACI

DoktorKrossOption: D
Mar 30, 2023

RACI and RAM charts are technically the same. But for the sake of BABOK, it should be RACI because the Responsibility Assignment Matrix is under PMBOK.

Hong_iOption: B
Sep 13, 2022

Couldn't find RAM in V3

Dillon91Option: D
Jan 30, 2023

RACI chart

Farooq_95Option: D
Apr 23, 2024

The question pertains to PMBOK. Its V7 defines Responsibility Assignment Matrix (RAM) as a grid that shows the project resources assigned to each work package. In the context of BABOK v3, RACI chart is correct answer because it involves assigning the RACI designation in order to specify the level of responsibility expected from each stakeholder and/or group. BABOK v3 does not define RAM.