Which of the following authorizes the project to exist within the organization?
Which of the following authorizes the project to exist within the organization?
The project charter is a document that officially authorizes the existence of a project within an organization. It provides the project manager with the authority to apply organizational resources to the project activities. This document typically includes the project's purpose, objectives, high-level requirements, and key stakeholders, among other elements. None of the other options listed serve the purpose of authorizing a project within an organization.
I don't know if this type of question will appear on the CBAP exam, as they pertain to Project Management not Business Analysis.
This is so true I have seen so many of them stated here
It doesn't exist in the exam, not in the way this question is phrased (if at all)