Question 288

During a requirements review, the implementation subject matter expert (SME) identified the requirement 'parsing of data' that must be implemented before other requirements. The business analyst (BA) has given this requirement high priority.

What factor influenced the prioritization of the requirement?

    Correct Answer: C

    The factor that influenced the prioritization of the requirement is dependencies. Dependencies refer to the relationships between requirements where the completion of one requirement is necessary before another can be fulfilled. In this scenario, the 'parsing of data' must be implemented before other requirements, indicating a dependency.

Discussion
cc2104Option: C

Ans C 5.3.4.1 Dependencies: relationships between requirements where one requirement cannot be fulfilled unless the other requirement is fulfilled. In some situations, it may be possible to achieve efficiencies by implementing related requirements at the same time. Dependencies may also be external to the initiative, including but not limited to other teams’ decisions, funding commitments, and resource availability.

rupakarthikOption: C

Dependencies: relationships between requirements where one requirement cannot be fulfilled unless the other requirement is fulfilled. BAbok Page-88