CBAP Exam QuestionsBrowse all questions from this exam

CBAP Exam - Question 290


After releasing its beta version of a travel assistance mobile application, a travel company has received feedback from a public survey proposing new features.

The company is struggling with the large number of ideas and would like to make a decision on which to consider in the next implementation cycle.

Which of the following considerations should be used first for filtering ideas?

Show Answer
Correct Answer: AC

When deciding which new features to implement, the first consideration should be the alignment with the solution scope. Ensuring that the proposed features align with the overall goals and purpose of the mobile application is crucial. Features that do not align with the solution scope should be eliminated or the future state re-evaluated, as they might not contribute to the desired outcomes. This alignment ensures that the development efforts are focused on delivering value to users and achieving the business objectives.

Discussion

9 comments
Sign in to comment
DoomsdayNairOption: C
Jan 20, 2021

C. Alignment with solution scope

cc2104Option: C
Aug 21, 2021

Ans C 7.3.4.3 A requirement can be of benefit to a stakeholder and still not be a desirable part of a solution. A requirement that does not deliver benefit to a stakeholder is a strong candidate for elimination. When requirements do not align, either the future state must be re-evaluated and the solution scope changed, or the requirement removed from the solution scope. If a design cannot be validated to support a requirement, there might be a missing or misunderstood requirement, or the design must change.

rhsdealOption: C
Apr 12, 2021

ANS is C BABOK V-3 3.4.6 pg 146 Evaluate Alignment with Solution Scope - A requirement can be of benefit to a stakeholder and still not be a desirable part of a solution. A requirement that does not deliver benefit to a stakeholder is a strong candidate for elimination. When requirements do not align, either the future state must be re-evaluated and the solution scope changed, or the requirement removed from the solution scope. If a design cannot be validated to support a requirement, there might be a missing or misunderstood requirement, or the design must change.

MmotunOption: A
May 19, 2022

It is A. This is solution evaluation. It is in beta stage, meaning a form.ofnthe solution exists and is being evaluated using survey. First filter will be highest customer satisfaction.

Nandu2023Option: C
Feb 17, 2023

C. Alignment with solution scope A requirement can be of benefit to a stakeholder and still not be a desirable part of a solution. A requirement that does not deliver benefit to a stakeholder is a strong candidate for elimination. When requirements do not align, either the future state must be re-evaluated and the solution scope changed, or the requirement removed from the solution scope

Pank_HDOption: A
May 15, 2022

A is correct : Benefits of a non-financial nature (such as improved staff morale, increased flexibility to respond to change, improved customer satisfaction, or reduced exposure to risk) are also important and add significant value to the organization.

v72Option: A
Jul 16, 2022

I'll go with A. Typical factors that influence prioritization include: • Benefit: the advantage that accrues to stakeholders as a result of requirement implementation, as measured against the goals and objectives for the change. The benefit provided can refer to specific functionality, desired quality, or strategic goal or business objective.

WlkkkkOption: C
Dec 11, 2022

keyword is 'beta version', the project is not officially delivered yet. need to consider solution scope prior to delivering additional features to increase client satisfaction.

RabbitsfootOption: C
Apr 1, 2024

C. ensures that the selected features align with the overall purpose and goals of the mobile application, increasing the likelihood of delivering value to users and achieving business objectives.