Question 211

Which of the following techniques involves coordinating and collaborating with other credible sources in risk?

    Correct Answer: C

    Risk communication involves the real-time exchange of information, advice, and opinions among individuals, experts, and officials, which is essential for coordinating and collaborating with credible sources in risk situations. This technique facilitates informed decision-making and promotes the adoption of protective behaviors.

Discussion
JeffduOption: B

The answer is B - Risk management, BABOK page 329

rhsdealOption: B

V-3 10.38.2 Risk Analysis and Management – (…)Risk management is an ongoing activity. Continuous consultation and communication with stakeholders helps to both identify new risks and to monitor identified risks. Risk Communication is not found in either BABOK V-2 or V-3

NickMane

thanks for the heads-up

Farooq_95Option: A

Risk identification is correct because of following 2 reasons: (1) Risk Identification is a term specifically used in BABOK v3 10.38.3.1 and involves combination of expert judgment, stakeholder input (in form of collaboration), experimentation, past experiences, and historic analysis. (2) As per BABOK v3 10.38.2, continuous and communication with stakeholders helps both identify new risk (i.e., Risk Identification) and to monitor identified risks.

JerryMag4Option: C

The answer is C, according to ChatGPT

JerryMag4

Sorry i meant the answer is Risk Management, B

DFUOption: A

10.38.3 Elements .1 Risk Identification Risks are discovered and identified through a combination of expert judgment, stakeholder input, experimentation, past experiences, and historical analysis of similar initiatives and situations. The goal is to identify a comprehensive set of relevant risks and to minimize the unknowns. Risk identification is an ongoing activity. Risk Analysis and Management Techniques 329

CBAPCohort6

Risk management is an ongoing activity. Continuous consultation and communication with stakeholders helps to both identify new risks and to monitor identified risks, correct answer is B. Check 10.38.2

MFZZOption: C

Key word - Collaboration

OctavianGOption: C

Risk communication refers to the real-time exchange of information, advice and opinions between experts, officials and people who face a threat to their wellbeing, to enable informed decision-making and to adopt protective behaviors

OctavianG

some of these questions don't appear in babok and is a normal thing. for example, some questions came from PMP, i